CONSTRUCTION LAW 
 Septic Tanks, Cisterns • Steps, Blocks, Planters • Parking Curbs, Barriers 
 Custom Arch., Structural • Catch Basin, Sump, Dykes • Burial Vaults, Memorial 
 Electrical Boxes, Bases • Fence/Soundwalls • Retaining Wall Block 
 Storm & Sanitary • Manholes • Sandwich Panels • Precast Grade Beams 
 Serving  
 Saskatchewan 
 Since 1988 
 T: 306-931-9229  
 F: 306-931-4447 
 3320 Idylwyld Drive N   
 Saskatoon, SK 
 For more information, visit us online at 
 www.preconltd.ca 
 The Court of  
 Appeal decision 
 The Court of Appeal overturned the Chamber  
 Judge’s  decision,  finding  the  claim  was  commenced  
 outside the limitation period and was  
 statute-barred.  According  to  the  Court,  the  
 limitation  period  began  to  run  in  July  2011  
 because this was when the discoverability requirements  
 were first met, specifically:  
 (a)	 Venture suffered the loss identified in the  
 claim as soon as it was required to undertake  
 remediation work. The fact Venture  
 had hope, or an expectation, it would  
 be compensated by the Ministry under  
 the contract does not change the fact  
 Venture knew it suffered a loss as a result  
 of incurring the cost of remediating the  
 subgrade work; and 
 (b)	 It was appropriate for Venture to   
 commence a legal proceeding against   
 the Ministry because there was no evidence  
 that:  
 (i)	 Venture actually sought to invoke  
 the provisions of the contract,  
 such as the Extra Work clause, prior  
 to requesting compensation in  
 December 2013; 
 (ii)	 Venture’s delay in bringing the action  
 was because it pursued an alternative  
 dispute mechanism; and  
 (iii)	Venture’s ability to complete work  
 on the project would have been impacted  
 or delayed by issuing and  
 prosecuting a claim. 
 In other words, all the facts accepted by the  
 Chambers  Judge  illustrated,  as  of  July  2011,  
 the  four  discoverability  requirements  of  the  
 Act were satisfied, specifically:  
 (a)	 Venture’s loss was identifiable;  
 (b)	 The Ministry’s conduct appeared to have  
 caused Venture’s loss;  
 (c)	 The Ministry was responsible for the  
 loss; and  
 (d)	 As of July 2011, it was appropriate for  
 Venture to commence an action. 
 The  Court  of  Appeal  reversed  the  lower  
 court’s  decision  and  dismissed  Venture’s  
 claim against the Ministry in its entirety. The  
 Ministry  was  awarded  a  portion  of  its  legal  
 costs at both levels. 
 The Court of Appeal overturned the  
 Chamber Judge’s decision, finding the claim  
 was commenced outside the limitation  
 period and was statute-barred. 
 Key takeaways 
 Missing  a  limitation  period  is  fatal  to  your  
 claim. If you suspect you have suffered a loss  
 or  damages,  you  should  always  ask  yourself  
 the  following  questions  to  ensure  you  meet  
 the applicable limitation period: 
 •	Can you identify: (1) the loss or damage;  
 (2) the cause of the loss or damage; and, (3)  
 the party responsible for the loss or damage? 
 •	Does your contract contain an alternative  
 dispute mechanism and, if it does, have you  
 advised the other party of your intention to  
 pursue such mechanism? 
 •	If you made a request for payment, did  
 your request specifically reference which  
 contractual provision you were relying on? 
 If you experience any issues during a project  
 related to the questions above, you should  
 reach out to your counsel to determine whether  
 a limitation period has begun.  
 Disclaimer: This publication is provided  
 as an information service and may include  
 items reported from other sources. We do not  
 warrant its accuracy. This information is not  
 meant as legal opinion or advice. If you have  
 any questions, please contact Troy Baril at  
 tbaril@millerthomson.com or 306-667-5630.  
 thinkbigmagazine.ca  |  Quarter 3 2020  |  Think BIG  43 
 
				
/www.preconltd.ca
		/thinkbigmagazine.ca
		link